Description: Learn how to bring the Schilling High-Light laser marking workstation into operation safely after installation or transport.
Preconditions
Confirm the following before applying power:
- All packaging material has been removed.
- All transport locks have been removed.
- The High-Light is standing upright in its intended operation position.
- Supply voltage and frequency have been checked against the machine requirements.
- The mains cable and plug are undamaged.
- The main switch is in the OFF position before connecting the power cable.
- The laser protection window is undamaged.
- Optical components are free from dust and contamination.
- The protective cover has been removed from the focusing objective.
- All required laser-safety measures have been implemented and verified.
The operating environments must also meet the High-Light requirements:
- Ambient temperature: +15 °C to +35 °C.
- Relative humidity: maximum 90%, non condensing.
- If the system has experienced significant temperature changes during transport, allow it to return to room temperature before commissioning.
- Avoid shocks, vibration and other mechanical stress.
- Keep the