1 This guide summarizes how to **receive**, **move**, **unpack**, **and prepare **the Multi-Light or Multi-Light PLUS for commissioning, using the terminology and sequence from the original manual.
2
3 = After Delivery: Unloading and Inspection =
4
5 After unloading, **inspect **the machine and all parts for transport damage, **check **screws/fittings, **verify **delivery completeness, and **remove **the transport packaging. If there's damage or missing items, **record details** **in writing immediately,** note it on the freight papers, **photograph **the damage, and** send a report to Schilling Marking Systems GmbH**.
6
7 (% class="box warningmessage" %)
8 (((
9 **Caution**: **Do not remove the lens unit cover until installation is complete. The optics are high-grade components; a flawless state is essential for optimal marking results.**
10 )))
11
12
13 = Transport =
14
15 ==== Shipping: ====
16
17 * The Multi-light and Multi-Light PLUS **must be transported in a carton on a pallet**. Secure the palletized carton against **slipping and tipping**. Use a suitable forklift for the machine's weight to unload.
18
19 ==== In-plant transport: ====
20
21 * Transport **upright **only; **avoid strong vibrations/shock**.
22 * Switch the system **off** at the main switch; **disconnect **power and **remove **the exhaust unit.
23 * Slightly** lift with a suitable forklift**, reposition, and place on an **even**, **clean floor**.
24 * After transport, re-align the system and perform initial electrical start-up and a function test.
25 * For long-distance shipping, **repack exactly as delivered**, including the** door transport lock**.
26
27
28
29 = Unpacking =
30
31 Unpacking must be performed by **qualified personnel**:
32
33 1. Place the palletized carton **upright on level ground** (use a suitable forklift).
34 1. **Release **the black tension straps.
35 1. **Remove **the carton and all packaging material (two persons required).
36
37
38
39 = Installation (Mechanical and Electrical) =
40
41 Before installation, ensure all **packaging and transport locks are removed** and the system is placed **upright**. After that:
42
43 * **Verify **mains voltage and frequency.
44 * **Inspect **the power cord and plug for damage; **replace is necessary**.
45 * Ensure the main switch on the operator panel is in position "**OFF**" **before **plugging in.
46 * **Check **the laser protection window for damage.
47
48
49
50 = Environmental Requirements =
51
52 * Ambient temperature **+15C to +35C**; relative humidity **<90% (non-condensing)**.
53 * If the system experienced major temperature fluctuations,** allow it to reach room temperature** before use.
54 * The laser system contains high-value** electrical and optical components **- avoid **mechanical loads**, **shocks**, **and vibrations**.
55 * Ensure **sufficient airflow** at both 19" drawer; **blocked vents or filter mats** can cause heat build-up and damage
56 **Note for extraction**:  Provide suitable** fume and dust extraction **to prevent hazards to personnel and the environment and to protect the working optics from deposits. Refer to workplace air quality guidance (e.g., **VDI 2262**). Schilling extraction units are recommended.
57
58
59
60 = Pre-Start Checklist =
61
62 To ensure a correct installation, verify:
63
64 * **Electrical installation** complete and** input voltage correct**.
65 * **Optical components** free of dust and contamination.
66 * **Lens/focus objective cover** has been **removed**.
67 * **Ambient conditions** meet the technical specifications.