This article summarizes the normal operating sequence for the Multi-Light workstation: switching on, running a marking job, and switching off. Only trained personnel may operate the system. Observe all safety notes before use.
Before You Start
- Ambient conditions within specifications; system acclimatized if there were temperature changes.
- Machine upright; transport locks removed; airflow at the 19" drawers unobstructed; filter mats clean.
- Laser protection window intact; protective housing and door interlocks OK.
- Fume/dust extraction ready.
Switch On
- Verify mains voltage/frequency and cable conditions; mains switch is OFF.
- Connect the machine, then set the main switch to ON to power electronics.
- Start the control PC and launch the supplied marking software (we recommend AnyMarker Designer