Last modified by jadomatis on 2025/10/08 11:08

From version 3.2
edited by jadomatis
on 2025/10/03 14:27
Change comment: There is no comment for this version
To version 1.16
edited by jadomatis
on 2025/09/29 13:08
Change comment: There is no comment for this version

Summary

Details

Page properties
Content
... ... @@ -1,90 +3,46 @@
1 -This procedure describes how to bring the Multi-Light or Multi-Light PLUS workstations into operation safely after transport or installation. **Only qualified personnel **may commission the system. Observer all safety notes before switching on.
2 -
3 3  = Preconditions (Before Switching On) =
4 4  
5 5  Confirm the following before applying power:
6 6  
7 -* **Electrical installation is correct**; mains **voltage and frequency **match the rating place. Main switch is OFF.
8 -* **Protective housing** and **door interlocks** are intact; **laser viewing window** shows now damage.
9 -* **Optics are clean**; remove any **transport/lens cover** only now. Avoid touching optics with bare hands.
10 -* **Ambient conditions**: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport.
11 -* **Airflow **at 19" drawers is unobstructed; **filter mats** are clean to prevent heat build-up.
12 -* **Fume extraction **is installed and operational (mandatory for personnel safety and to protect optics).
13 -* Operator is familiar with **laser safety** requirements; responsibilities are defined.
14 -**Note**: The Multi-Light contains a **Class 4 **source operated as **Class 1** in the closed cabin. Never bypass safety devices.
5 +* Electrical installation is correct; mains voltage and frequency match the rating place. Main switch is OFF.
6 +* Protective housing and door interlocks are intact; laser viewing window shows now damage.
7 +* Optics are clean; remove any transport/lens cover only now. Avoid touching optics with bare hands.
8 +* Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport.
9 +* Airflow at 19" drawers is unobstructed; filter mats are clean to prevent heat build-up.
10 +* Operator is familiar with laser safety requirements; responsibilities are defined.
11 +Note: The Multi-Light contains a Class 4 source operated as Class 1 in the closed cabin. Never bypass safety devices.
15 15  
16 16  
17 17  
18 18  = Electrical Start-Up =
19 19  
20 -1. Connect the system to the specified **mains supply**. Ensure extraction is running.
21 -1. Set the **mains switch to ON**. Internal electronics initialize; status indicators light as described on the operator panel.
22 -1. Power on the **control PC** (or workstation) and peripherals needed for operation.
17 +1. Connect the system to the specified mains supply. Ensure extraction is running.
18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel.
19 +1. Power on the control PC (or workstation) and peripherals needed for operation.
23 23  
24 24  
25 25  
26 26  = Software and Device Connection =
27 27  
28 -1. Launch the **AnyMarker Designer **software.
29 -1. Verify communication with the **laser controller** in the software (device connected, parameters readable).
30 -If connection fails, switch **OFF**, check cabling and restart.
25 +1. Launch the AnyMarker Designer software.
26 +1. Verify communication with the laser controller in the software (device connected, parameters readable).
27 +If connection fails, switch OFF, check cabling and restart.
31 31  
32 -{{warning}}
33 -**Important: Only start the laser software when the laser is switched on. If the laser is switched on while the software is running, the system will not work.**
34 -{{/warning}}
35 35  
36 36  
37 37  = Initial Checks With Pilot Laser =
38 38  
39 -* Load or create a **test layout** in AnyMarker Designer.
40 -* Enable the** pilot laser **to project contours on the workpiece; verify **orientation and placement** without laser emission. Keep the door closed.
33 +* Load or create a test layout in AnyMarker Designer.
34 +* Enable the pilot laser to project contours on the workpiece; verify orientation and placement without laser emission. Keep the door closed.
41 41  
42 42  
43 43  
44 44  = Z-Axis Focusing =
45 45  
46 -1. Place the workpiece/fixture in the work chamber and close the **manual lift door**.
47 -1. Use the **automatic Z-axis** to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height.
40 +1. Place the workpiece/fixture in the work chamber and close the manual lift door.
41 +1. Use the automatic Z-axis to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height.
48 48  1. Confirm best focus by pilot outline sharpness or focus gauge method recommended in the manual.
49 49  
50 50  
51 51  
52 -= Parameter Verification =
53 -
54 -* Select a verified **marking parameter set** (power, speed, frequency, fill). Start with conservative energy to avoid burning or glare.
55 -* Ensure extraction is active to remove **gases**, **vapors**, **aerosols**, **and dust** during test marking.
56 -
57 -
58 -
59 -= First Test Mark =
60 -
61 -1. With the cabin closed and interlocks engaged, execute a **short test mark** on a sample of the target material.
62 -1. Observe quality and adjust **parameters **(e.g., reduce power/increase speed) as needed. Multiple **repetitions **may be used for depth, but monitor temperature to reduce fire risk.
63 -1. If unexpected behavior occurs, press **STOP**/**EMERGENCY-STOP**, investigate messages in **Notifications**, and correct the cause before resuming.
64 -
65 -
66 -
67 -= Post-Test Verification =
68 -
69 -* Inspect the mark; check legibility/contrast. Clean light residue if necessary.
70 -* Re-check **filters**/**airflow **after prolonged tests. Excess dust must not accumulate.
71 -* Document the **approved parameter set** for production.
72 -
73 -
74 -
75 -= Normal Operation Handover =
76 -
77 -* Train operators on **door interlock**, **pilot laser**, **start**/**stop**, and **notifications **usage.
78 -* Emphasize daily** pre-shift checks **(visible damage, labels present, safety devices functional).
79 -
80 -
81 -
82 -= Shutdown (End of Day) =
83 -
84 -1. Stop software and close the project.
85 -1. Turn the system **OFF **via main switch; power down extraction as specified.
86 -1. Clean the work area; never leave the machine **unattended **while powered.
87 -
88 -
89 -
90 90