Changes for page Commissioning and First Start-Up
Last modified by jadomatis on 2025/10/08 11:08
Summary
-
Page properties (1 modified, 0 added, 0 removed)
Details
- Page properties
-
- Content
-
... ... @@ -1,47 +3,44 @@ 1 -This procedure describes how to bring the Multi-Light workstation into operation safely after transport or installation. **Only qualified personnel **may commission the system. Observer all safety notes before switching on. 2 - 3 3 = Preconditions (Before Switching On) = 4 4 5 5 Confirm the following before applying power: 6 6 7 -* **Electrical installation is correct**; mains **voltage and frequency **match the rating place. Main switch is OFF. 8 -* **Protective housing** and **door interlocks** are intact; **laser viewing window** shows now damage. 9 -* **Optics are clean**; remove any **transport/lens cover** only now. Avoid touching optics with bare hands. 10 -* **Ambient conditions**: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. 11 -* **Airflow **at 19" drawers is unobstructed; **filter mats** are clean to prevent heat build-up. 12 -* **Fume extraction **is installed and operational (mandatory for personnel safety and to protect optics). 13 -* Operator is familiar with **laser safety** requirements; responsibilities are defined. 14 -**Note**: The Multi-Light contains a **Class 4 **source operated as **Class 1** in the closed cabin. Never bypass safety devices. 5 +* Electrical installation is correct; mains voltage and frequency match the rating place. Main switch is OFF. 6 +* Protective housing and door interlocks are intact; laser viewing window shows now damage. 7 +* Optics are clean; remove any transport/lens cover only now. Avoid touching optics with bare hands. 8 +* Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. 9 +* Airflow at 19" drawers is unobstructed; filter mats are clean to prevent heat build-up. 10 +* Operator is familiar with laser safety requirements; responsibilities are defined. 11 +Note: The Multi-Light contains a Class 4 source operated as Class 1 in the closed cabin. Never bypass safety devices. 15 15 16 16 17 17 18 18 = Electrical Start-Up = 19 19 20 -1. Connect the system to the specified **mains supply**. Ensure extraction is running.21 -1. Set the **mains switch to ON**. Internal electronics initialize; status indicators light as described on the operator panel.22 -1. Power on the **control PC**(or workstation) and peripherals needed for operation.17 +1. Connect the system to the specified mains supply. Ensure extraction is running. 18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel. 19 +1. Power on the control PC (or workstation) and peripherals needed for operation. 23 23 24 24 25 25 26 26 = Software and Device Connection = 27 27 28 -1. Launch the **AnyMarker Designer**software.29 -1. Verify communication with the **laser controller**in the software (device connected, parameters readable).30 -If connection fails, switch **OFF**, check cabling and restart.25 +1. Launch the AnyMarker Designer software. 26 +1. Verify communication with the laser controller in the software (device connected, parameters readable). 27 +If connection fails, switch OFF, check cabling and restart. 31 31 32 32 33 33 34 34 = Initial Checks With Pilot Laser = 35 35 36 -* Load or create a **test layout**in AnyMarker Designer.37 -* Enable the **pilot laser**to project contours on the workpiece; verify**orientation and placement**without laser emission. Keep the door closed.33 +* Load or create a test layout in AnyMarker Designer. 34 +* Enable the pilot laser to project contours on the workpiece; verify orientation and placement without laser emission. Keep the door closed. 38 38 39 39 40 40 41 41 = Z-Axis Focusing = 42 42 43 -1. Place the workpiece/fixture in the work chamber and close the **manual lift door**.44 -1. Use the **automatic Z-axis**to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height.40 +1. Place the workpiece/fixture in the work chamber and close the manual lift door. 41 +1. Use the automatic Z-axis to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height. 45 45 1. Confirm best focus by pilot outline sharpness or focus gauge method recommended in the manual. 46 46 47 47 ... ... @@ -48,16 +48,16 @@ 48 48 49 49 = Parameter Verification = 50 50 51 -* Select a verified **marking parameter set**(power, speed, frequency, fill). Start with conservative energy to avoid burning or glare.52 -* Ensure extraction is active to remove **gases**,**vapors**,**aerosols**,**and dust**during test marking.48 +* Select a verified marking parameter set (power, speed, frequency, fill). Start with conservative energy to avoid burning or glare. 49 +* Ensure extraction is active to remove gases, vapors, aerosols, and dust during test marking. 53 53 54 54 55 55 56 56 = First Test Mark = 57 57 58 -1. With the cabin closed and interlocks engaged, execute a **short test mark**on a sample of the target material.59 -1. Observe quality and adjust **parameters**(e.g., reduce power/increase speed) as needed. Multiple**repetitions**may be used for depth, but monitor temperature to reduce fire risk.60 -1. If unexpected behavior occurs, press **STOP**/**EMERGENCY-STOP**, investigate messages in**Notifications**, and correct the cause before resuming.55 +1. With the cabin closed and interlocks engaged, execute a short test mark on a sample of the target material. 56 +1. Observe quality and adjust parameters (e.g., reduce power/increase speed) as needed. Multiple repetitions may be used for depth, but monitor temperature to reduce fire risk. 57 +1. If unexpected behavior occurs, press STOP/EMERGENCY-STOP, investigate messages in Notifications, and correct the cause before resuming. 61 61 62 62 63 63 ... ... @@ -64,24 +64,4 @@ 64 64 = Post-Test Verification = 65 65 66 66 * Inspect the mark; check legibility/contrast. Clean light residue if necessary. 67 -* Re-check **filters**/**airflow **after prolonged tests. Excess dust must not accumulate. 68 -* Document the **approved parameter set** for production. 69 - 70 - 71 - 72 -= Normal Operation Handover = 73 - 74 -* Train operators on **door interlock**, **pilot laser**, **start**/**stop**, and **notifications **usage. 75 -* Emphasize daily** pre-shift checks **(visible damage, labels present, safety devices functional). 76 - 77 - 78 - 79 -= Shutdown (End of Day) = 80 - 81 -1. Stop software and close the project. 82 -1. Turn the system **OFF **via main switch; power down extraction as specified. 83 -1. Clean the work area; never leave the machine **unattended **while powered. 84 - 85 - 86 - 87 - 64 +* Re-check filters/airflow after