Changes for page Commissioning and First Start-Up
Last modified by jadomatis on 2025/10/08 11:08
Summary
-
Page properties (1 modified, 0 added, 0 removed)
Details
- Page properties
-
- Content
-
... ... @@ -15,4 +15,17 @@ 15 15 = Electrical Start-Up = 16 16 17 17 1. Connect the system to the specified mains supply. Ensure extraction is running. 18 -1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel 18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel. 19 +1. Power on the control PC (or workstation) and peripherals needed for operation. 20 + 21 + 22 + 23 += Software and Device Connection = 24 + 25 +1. Launch the AnyMarker Designer software. 26 +1. Verify communication with the laser controller in the software (device connected, parameters readable). 27 +If connection fails, switch OFF, check cabling and restart. 28 + 29 + 30 + 31 +