Summary

Details

Page properties
Content
... ... @@ -12,4 +12,14 @@
12 12  
13 13  
14 14  
15 -
15 += Electrical Start-Up =
16 +
17 +1. Connect the system to the specified mains supply. Ensure extraction is running.
18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel.
19 +1. Power on the control PC (or workstation) and peripherals needed for operation.
20 +
21 +
22 +
23 += Software and Device Connection =
24 +
25 +1. Launch the AnyMarker Dwai