Changes for page Commissioning and First Start-Up
Last modified by jadomatis on 2025/10/08 11:08
Summary
-
Page properties (1 modified, 0 added, 0 removed)
Details
- Page properties
-
- Content
-
... ... @@ -12,4 +12,12 @@ 12 12 13 13 14 14 15 += Electrical Start-Up = 16 + 17 +1. Connect the system to the specified mains supply. Ensure extraction is running. 18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel. 19 +1. Power on the control PC (or workstation) and peripherals needed for operation. 20 + 21 + 22 + 15 15