Changes for page Commissioning and First Start-Up
Last modified by jadomatis on 2025/10/08 11:08
Summary
-
Page properties (1 modified, 0 added, 0 removed)
Details
- Page properties
-
- Content
-
... ... @@ -8,4 +8,11 @@ 8 8 * Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. 9 9 * Airflow at 19" drawers is unobstructed; filter mats are clean to prevent heat build-up. 10 10 * Operator is familiar with laser safety requirements; responsibilities are defined. 11 -Note: The Multi-Light containe 11 +Note: The Multi-Light contains a Class 4 source operated as Class 1 in the closed cabin. Never bypass safety devices. 12 + 13 + 14 + 15 += Electrical Start-Up = 16 + 17 +1. Connect the system to the specified mains supply. Ensure extraction is running. 18 +1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel