Changes for page Commissioning and First Start-Up
Last modified by jadomatis on 2025/10/08 11:08
Summary
-
Page properties (2 modified, 0 added, 0 removed)
Details
- Page properties
-
- Parent
-
... ... @@ -1,1 +1,1 @@ 1 -Laser Marking Machines. Schilling Marking Systems Multi-Light.Getting Started.WebHome1 +Laser Marking Machines.Getting Started.WebHome - Content
-
... ... @@ -1,9 +1,95 @@ 1 +This procedure describes how to bring the Multi-Light or Multi-Light PLUS workstations into operation safely after transport or installation. 2 + 3 +(% class="box warningmessage" %) 4 +((( 5 +**Only qualified personnel may commission the system. Observe all safety notes before switching on.** 6 +))) 7 + 1 1 = Preconditions (Before Switching On) = 2 2 3 3 Confirm the following before applying power: 4 4 5 -* Electrical installation is correct; mains voltage and frequency match the rating place. Main switch is OFF. 6 -* Protective housing and door interlocks are intact; laser viewing window shows now damage. 7 -* Optics are clean; remove any transport/lens cover only now. Avoid touching optics with bare hands. 8 -* Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. 9 -* Airflow at 19" drawers is unobstructed; 12 +* **Electrical installation is correct**; mains **voltage and frequency **match the rating place. Main switch is OFF. 13 +* **Protective housing** and **door interlocks** are intact; **laser viewing window** shows now damage. 14 +* **Optics are clean**; remove any **transport/lens cover** only now. Avoid touching optics with bare hands. 15 +* **Ambient conditions**: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. 16 +* **Airflow **at 19" drawers is unobstructed; **filter mats** are clean to prevent heat build-up. 17 +* **Fume extraction **is installed and operational (mandatory for personnel safety and to protect optics). 18 +* Operator is familiar with **laser safety** requirements; responsibilities are defined. 19 +**Note**: The Multi-Light and Multi-Light PLUS both contain a **Class 4 **laser** **source operated as **Class 1** in the closed cabin. Never bypass safety devices. 20 + 21 + 22 + 23 += Electrical Start-Up = 24 + 25 +1. Connect the system to the specified **mains supply**. Ensure extraction is running. 26 +1. Set the **mains switch to ON**. Internal electronics initialize; status indicators light as described on the operator panel. 27 +1. Power on the **control PC** (or workstation) and peripherals needed for operation. 28 + 29 + 30 + 31 += Software and Device Connection = 32 + 33 +1. Launch the **AnyMarker Designer **software. 34 +1. Verify communication with the **laser controller** in the software (device connected, parameters readable). 35 +If connection fails, switch **OFF**, check cabling and restart. 36 + 37 +{{warning}} 38 +**Important: Only start the laser software when the laser is switched on. If the laser is switched on while the software is running, the system will not work.** 39 +{{/warning}} 40 + 41 + 42 += Initial Checks With Pilot Laser = 43 + 44 +* Load or create a **test layout** in AnyMarker Designer. 45 +* Enable the** pilot laser **to project contours on the workpiece; verify **orientation and placement** without laser emission. Keep the door closed. 46 + 47 + 48 + 49 += Z-Axis Focusing = 50 + 51 +1. Place the workpiece/fixture in the work chamber and close the **manual lift door**. 52 +1. Use the Z-axis adjustment to set the focus point according to the height of the marking surface. Upon delivery, the zero point is calibrated to the height of the base plate. The Z-axis moves to the correct point according to the parameters of the workpiece. Check the focus point and adjust if necessary. 53 +1. Confirm best focus by pilot outline sharpness or focus gauge method recommended in the manual. 54 + 55 + 56 + 57 += Parameter Verification = 58 + 59 +* Select a verified **marking parameter set** (power, speed, frequency, fill). Start with conservative energy to avoid burning or glare. 60 +* Ensure extraction is active to remove **gases**, **vapors**, **aerosols**, **and dust** during test marking. 61 + 62 + 63 + 64 += First Test Mark = 65 + 66 +1. With the cabin closed and interlocks engaged, execute a **short test mark** on a sample of the target material. 67 +1. Observe quality and adjust **parameters **(e.g., reduce power/increase speed) as needed. Multiple **repetitions **may be used for depth, but monitor temperature with a suitable temperature reading device to reduce fire risk. 68 +1. If unexpected behavior occurs, press **STOP**/**EMERGENCY-STOP**, investigate messages in **Notifications**, and correct the cause before resuming. 69 + 70 + 71 + 72 += Post-Test Verification = 73 + 74 +* Inspect the mark; check legibility/contrast. Clean light residue if necessary. 75 +* Re-check **filters**/**airflow **after prolonged tests. Excess dust must not accumulate. 76 +* Document the **approved parameter set** for production. 77 + 78 + 79 + 80 += Normal Operation Handover = 81 + 82 +* Train operators on **door interlock**, **pilot laser**, **start**/**stop**, and **notifications **usage. 83 +* Emphasize daily** pre-shift checks **(visible damage, labels present, safety devices functional). 84 + 85 + 86 + 87 += Shutdown (End of Day) = 88 + 89 +1. Stop software and close the project. 90 +1. Turn the system **OFF **via main switch; power down extraction as specified. 91 +1. Clean the work area; never leave the machine **unattended **while powered. 92 + 93 + 94 + 95 +