... ... @@ -53,28 +53,4 @@
53 53  = First Test Mark =
54 54  
55 55  1. With the cabin closed and interlocks engaged, execute a short test mark on a sample of the target material.
56 -1. Observe quality and adjust parameters (e.g., reduce power/increase speed) as needed. Multiple repetitions may be used for depth, but monitor temperature to reduce fire risk.
57 -1. If unexpected behavior occurs, press STOP/EMERGENCY-STOP, investigate messages in Notifications, and correct the cause before resuming.
58 -
59 -
60 -
61 -= Post-Test Verification =
62 -
63 -* Inspect the mark; check legibility/contrast. Clean light residue if necessary.
64 -* Re-check filters/airflow after prolonged tests. Excess dust must not accumulate.
65 -* Document the approved parameter set for production.
66 -
67 -
68 -
69 -= Normal Operation Handover =
70 -
71 -* Train operators on door interlock, pilot laser, start/stop, and notifications usage.
72 -* Emphasize daily pre-shift checks (visible damage, labels present, safety devices functional).
73 -
74 -
75 -
76 -= Shutdown (End of Day) =
77 -
78 -1. Stop software and close the project.
79 -1. Turn the system OFF via main switch; power down extraction as specified.
80 -1. Clean the work
56 +1. Observe quality and adjust paramete