Last modified by jadomatis on 2025/10/08 11:08

From version 1.11
edited by jadomatis
on 2025/09/29 12:22
Change comment: There is no comment for this version
To version 1.23
edited by jadomatis
on 2025/09/29 14:08
Change comment: There is no comment for this version

Summary

Details

Page properties
Content
... ... @@ -22,4 +22,50 @@
22 22  
23 23  = Software and Device Connection =
24 24  
25 -1. Launch the AnyMarker Dwai
25 +1. Launch the AnyMarker Designer software.
26 +1. Verify communication with the laser controller in the software (device connected, parameters readable).
27 +If connection fails, switch OFF, check cabling and restart.
28 +
29 +
30 +
31 += Initial Checks With Pilot Laser =
32 +
33 +* Load or create a test layout in AnyMarker Designer.
34 +* Enable the pilot laser to project contours on the workpiece; verify orientation and placement without laser emission. Keep the door closed.
35 +
36 +
37 +
38 += Z-Axis Focusing =
39 +
40 +1. Place the workpiece/fixture in the work chamber and close the manual lift door.
41 +1. Use the automatic Z-axis to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height.
42 +1. Confirm best focus by pilot outline sharpness or focus gauge method recommended in the manual.
43 +
44 +
45 +
46 += Parameter Verification =
47 +
48 +* Select a verified marking parameter set (power, speed, frequency, fill). Start with conservative energy to avoid burning or glare.
49 +* Ensure extraction is active to remove gases, vapors, aerosols, and dust during test marking.
50 +
51 +
52 +
53 += First Test Mark =
54 +
55 +1. With the cabin closed and interlocks engaged, execute a short test mark on a sample of the target material.
56 +1. Observe quality and adjust parameters (e.g., reduce power/increase speed) as needed. Multiple repetitions may be used for depth, but monitor temperature to reduce fire risk.
57 +1. If unexpected behavior occurs, press STOP/EMERGENCY-STOP, investigate messages in Notifications, and correct the cause before resuming.
58 +
59 +
60 +
61 += Post-Test Verification =
62 +
63 +* Inspect the mark; check legibility/contrast. Clean light residue if necessary.
64 +* Re-check filters/airflow after prolonged tests. Excess dust must not accumulate.
65 +* Document the approved parameter set for production.
66 +
67 +
68 +
69 += Normal Operation Handover =
70 +
71 +* Train operators on door interl