Transportation and Installation

Version 3.3 by jadomatis on 2026/09/01 12:19

Description: Learn how to transport, unpack, position and prepare High-Light laser marking system for commisioning.


Transportation, unpacking, and installation must only be performed by qualified personnel using suitable lifting and handling equipment.

After Delivery: Unloading and Inspection

After unloading the High-Light:

  • Inspect the machine and its components for visible transport damage.
  • Check screws, fasteners, and connections for damage or loosening.
  • Verify that the delivery is complete.
  • Inspect the transport packaging for evidence of impact, tilting, or mishandling.

 If damage or missing components are discovered:

  1. Record the details immediately in writing.
  2. Note the damage or missing items on the freight documentation
  3. Photograph the affected packaging and machine components.
  4. Send a report to Schilling Marking Systems GmbH.

Do not commission a visibly damaged system. 

Caution: Keep the protective cover on the lens unit until installation is complete. The optical components are sensitive, and their condition directly affects the marking results.

Transport

Shipping and Long-Distance Transport

The High-Light must be transported in the original packaging around its wheeled base frame.

  • Keep the machine upright.
  • Secure the packaged system against slipping and tipping.
  • Use a forklift suitable for the total machine and packaging weight.
  • Avoid impacts, strong vibrations, and mechanical loads.
  • Reinstall the door transport restraint before long-distance transport.
  • Whenever possible, package the system exactly as it was delivered.

Do not transport the High-Light while it is connected to the electrical supply or extraction system.

In-Plant Transport

Avoid strong impacts, vibrations, or sudden movements during transport.

After repositioning, the High-Light must be realigned. The electrical system must be recommissioned and a functional test must be completed before production resumes.

Before moving the High-Light within the facility:

  1. Finish or safely stop all active marking operations.
  2. Close marking software.
  3. Switch off the system using main switch.
  4. Disconnect the electrical supply cable.
  5. Disconnect and remove the extraction connection.
  6. Secure the lifting door and other movable components as required.
  7. Use a suitable forklift to lift the machine slightly.
  8. Move the machine while keeping it upright.
  9. Place it on a level, clean, and stable floor.

Unpacking

Retain the original packaging and door transport restraint for future long-distance tranports.

The High-Light must only be unpacked by qualified personnel.

At least two people are required to remove the transport packaging safely.

  1. Place the packaged machine upright on level ground using a suitable forklift.
  2. Make sure the package is stable before opening it.
  3. Remove the protective film.
  4. Carefully remove the carton and remaining packaging material.
  5. Release and remove the transport restraints.
  6. Check the machine again for concealed transport damage.
  7. Verify that no packaging material remains inside or around the machine.

Open and remove the carton carefully to prevent packaging sections from tipping or falling.

Mechanical And Electrical Installation

Place the High-Light in it's intended operating location.

The installation location must:

  • Have a level, clean, and stable floor.
  • Provide sufficient space for operating and servicing the machine.
  • Allow the lifting door to move through its complete travel without obstruction.
  • Provide sufficient clearance around the ventilation openings.
  • Allow safe access to the main switch and Emergency Stop.
  • Provide a suitable connection for the extraction system.
  • Protect the system from impacts, excessive vibration, moisture, and contamination.

Positioning The High-Light

Before connecting the system:

  • Remove all packaging and transport restraints
  • Make sure the High-Light is upright and correctly alligned.
  • Inspect the electrical supply cable and plug for damage.
  • Verify that the available mains voltage and frequency match the machine requirements.
  • Make sure the main switch on the operating panel is in the OFF position.
  • Check the laser protection window for cracks, scratches, or other damage.
  • Check that all housing panel and protective components are installed securely.
  • Check that optical components are free from dust and contamination.
  • Confirm that the protective cover remains on the focusing lens until the installation work is complete.

After completing these checks:

  1. Connect the extraction system.
  2. Connect the electrical supply.
  3. Remove the protective cover from the focusing lens.
  4. Check that the automatic lifting door is unobstructed.
  5. Check that the X-, Y-, and Z-axis travel areas are clear.
  6. Prepare the system for electrical commissioning and functional testing.

Do not manually force the lifting door or any software control axis.

Environmental Requirements

The installation location must meet the following conditions:

  1. Ambient temperature between +15 C and +35 C.
  2. Relative humidity not exceeding 90%, non-condensing.
  3. Sufficient ventilation around the system.
  4. Unobstructed airflow at the electronic modules, ventilation openings, filter mats.
  5. Suitable extraction for fumes, vapors, aerosols, and particles generated during marking.

If the High-Light has been exposed to significant temperature changes, allow it to reach room temperature before switching it on.

Mechanical loads, impacts, and vibrations must be avoided because the system contains sensitive electrical and optical components. 

Pre-Commissioning Checklist

Before the High-Light is switched on for the first time, verify that:

  • The electrical installation is complete.
  • The input voltage and frequency are correct.
  • The machine is correctly positioned and alligned.
  • All packaging and transport restraints have been removed.
  • The lifting door can move without obstruction.
  • The X-, Y-, Z-axis travel areas are clear.
  • The extraction system is connected and ready.
  • The laser protection window is undamaged,
  • All protective panels are present and secured.
  • The optical components are clean.
  • The protective lens coved has been removed.
  • The environment conditions meet the technical specifications.
  • All required laser safety measures have been implemented.
  • The operating personnel are familiar with the applicable laser safety requirements.

 The High-Light may only be switched on after an authorized person has verified that the installation and all laser safety provisions comply with the applicable requirements.

After Repositioning or Transport

After any transport or significant repositioning:

  1. Inspect the machine for damage.
  2. Confirm that the machine is level and correctly aligned.
  3. Check all electrical and extraction connections.
  4. Check the lifting-door safety function.
  5. Check the Emergency Stop.
  6. Perform the required axis reference movements.
  7. Perform an electrical recommissioning check.
  8. Complete a functional test before returning the machine to production.

If the machine was damaged, tilted, subjected to a significant impact, or cannot be recommissioned normally, keep it switched off and contact Schilling Marking Systems or authorized service personnel.

Make sure the monitor arm, keyboard holder, lifting door, and other movable components can be used without striking walls, equipment, or surrounding objects.