Description: Learn how to transport, unpack, position and prepare High-Light laser marking system for commisioning.
After Delivery: Unloading And Inspection
After unloading the High-Light:
- Inspect the machine and its components for visible transport damage.
- Check screws, fasteners, and connections for damage or loosening.
- Verify that the delivery is complete.
- Inspect the transport packaging for evidence of impact, tilting, or mishandling.
If damage or missing components are discovered:
- Record the details immediately in writing.
- Note the damage or missing items on the freight documentation
- Photograph the affected packaging and machine components.
- Send a report to Schilling Marking Systems GmbH.
Transport
Shipping and Long-Distance Transport
The High-Light must be transported in the original packaging around its wheeled base frame.
- Keep the machine upright.
- Secure the packaged system against slipping and tipping.
- Use a forklift suitable for the total machine and packaging weight.
- Avoid impacts, strong vibrations, and mechanical loads.
- Reinstall the door transport restraint before long-distance transport.
- Whenever possible, package the system exactly as it was delivered.
Do not transport the High-Light while it is connected to the electrical supply or extraction system.
In-Plant Transport
Before moving the High-Light within the facility:
- Finish or safely stop all active marking operations.
- Close marking software.
- Switch off the system using main switch.
- Disconnect the electrical supply cable.
- Disconnect and remove the extraction connection.
- Secure the lifting door and other movable components as required.
- Use a suitable forklift to lift the machine slightly.
- Move the machine while keeping it upright.
- Place it on a level, clean, and stable floor.
After repositioning, the High-Light must be realigned. The electrical system must be recommissioned and a functional test must be completed before production resumes.
Unpacking
The High-Light must only be unpacked by qualified personnel.
At least two people are required to remove the transport packaging safely.
- Place the packaged machine upright on level ground using a suitable forklift.
- Make sure the package is stable before opening it.
- Remove the protective film.
- Carefully remove the carton and remaining packaging material.
- Release and remove the transport restraints.
- Check the machine again for concealed transport damage.
- Verify that no packaging material remains inside or around the machine.
Open and remove the carton carefully to prevent packaging sections from tipping or falling.
Positioning The High-Light
Place the High-Light in it's intended operating location.
The installation location must:
- Have a level, clean, and stable floor.
- Provide sufficient space for operating and servicing the machine.
- Allow the lifting door to move through its complete travel without obstruction.
- Provide sufficient clearance around the ventilation openings.
- Allow safe access to the main switch and Emergency Stop.
- Provide a suitable connection for the extraction system.
- Protect the system from impacts, excessive vibration, moisture, and contamination.
Mechanical And Electrical Installation
Before connecting the system:
- Remove all packaging and transport restraints
- Make sure the High-Light is upright and correctly alligned.
- Inspect the electrical supply cable and plug for damage.
- Verify that the available mains voltage and frequency match the machine requirements.
- Make sure the main switch on the operating panel is in the OFF position.
- Check the laser protection window for cracks, scratches, or other damage.
- Check that all housing panel and protective components are installed securely.
- Check that optical components are free from dust and contamination.
- Confirm that the protective cover remains on the focusing lens until the installation work is complete.
After completing these checks:
- Connect the extraction system.
- Connect the electrical supply.
- Remove the protective cover from the focusing lens.
- Check that the automatic lifting door is unobstructed.
- Check that the X-, Y-, and Z-axis travel areas are clear.
- Prepare the system for electrical commissioning and functional testing.
Do not manually force the lifting door or any software control axis.
Environmental Requirements
The installation location must meet the following conditions:
- Ambient temperature between +15 C and +35 C.
- Relative humidity not exceeding 90%, non-condensing.
- Sufficient ventilation around the system.
- Unobstructed airflow at the electronic modules, ventilation openings, filter mats.
- Suitable extraction for fumes, vapors, aerosols, and particles generated during marking.
Pre-Commissioning Checklist
Before the High-Light is switched on for the first time, verify that:
- The electrical installation is complete.
- The input voltage and frequency are correct.
- The machine is correctly positioned and alligned.
- All packaging and transport restraints have been removed.
- The lifting door can move without obstruction.
- The X-, Y-, Z-axis travel areas are clear.
- The extraction system is connected and ready.
- The laser protection window is undamaged,
- All protective panels are present and secured.
- The optical components are clean.
- The protective lens coved has been removed.
- The environment conditions meet the technical specifications.
- All required laser safety measures have been implemented.
- The operating personnel are familiar with the applicable laser safety requirements.
After Repositioning or Transport
After the