Last modified by jadomatis on 2026/09/01 08:14

From version 1.9
edited by jadomatis
on 2026/09/01 07:18
Change comment: There is no comment for this version
To version 1.22
edited by jadomatis
on 2026/09/01 08:08
Change comment: There is no comment for this version

Summary

Details

Page properties
Content
... ... @@ -39,6 +39,69 @@
39 39  The High-Light is now ready for job preparation.
40 40  
41 41  
42 -= Prepare the Marking Job =
42 += Prepare The Marking Job =
43 43  
44 -1.
44 +1. Perform the reference run required by the installed axis configuration.
45 +The standard High-Light configuration includes software-controlled X,Y and Z axes. Complete all reference movements requested by the control software before positioning the workpiece.
46 +1. Create a new marking file or open an approved existing file.
47 +1. Load the validated marking parameters for the workpiece material and required marking result.
48 +1. Set the Z-axis to the required focal height.
49 +1. Secure the workpiece in the appropriate fixture.
50 +1. Use the pilot laser to display the marking area or marking contours.
51 +1. Check that the marking is correctly positioned on the workpiece.
52 +1. Where the marking program uses X- and Y-axis movement, verify that the programmed axis positions and travel area are suitable for the installed fixture and workpiece.
53 +
54 +Do not start the marking process until the workpiece is securely positioned and the marking location has been verified.
55 +
56 +
57 += Run The Marking =
58 +
59 +1. Switch on the extraction system.
60 +1. Close the cabin door completely.
61 +1. Confirm that the yellow LED is illuminated. This indicated that the door safely circuit is satisfied.
62 +1. Check the marking software for active warnings or fault messages.
63 +1. Start the marking process.
64 +1. During the marking, the red laser-active LED should be illuminated.
65 +1. The programmed marking sequence runs automatically.
66 +1. Monitor the system during operation. Do not leave High-Light unattended.
67 +1. When the marking process is complete, the red LED switches off while the yellow LED remains illuminated.
68 +1. Open the lifting door using the normal machine controls and remove the marked workpiece.
69 +
70 +(% class="box warningmessage" %)
71 +(((
72 +Never open the cabin or attempt to access the work are while the red laser-active LED is illuminated.
73 +)))
74 +
75 +
76 +
77 += Check The Marking Results =
78 +
79 +Inspect the completed marking for:
80 +
81 +* Correct position
82 +* Legibility
83 +* Contrast
84 +* Completeness
85 +* Required marking depth or surface effect
86 +
87 +If the result is unsatisfactory, check the focal height, workpiece position, marking parameters, and selected marking file before repeating the process.
88 +
89 +Do not change validated production parameters without authorization.
90 +
91 +
92 += Shutdown =
93 +
94 +1. Allow the current marking process to finish or stop it safely through the marking software.
95 +1. Save the marking file and any required production data.
96 +1. Close the marking software on the control PC.
97 +1. Switch off the laser system using the main switch.
98 +1. Switch off the extraction system after any remaining fumes or particles have been removed from the cabin.
99 +1. Remove finished workpieces and unnecessary materials from the work area.
100 +1. Leave the cabin and surrounding work area clean.
101 +
102 +
103 +
104 += If The System Is Not Ready =
105 +
106 +* Green LED remains off:
107 +* Blue button remains illuminated: