1 **Description**: Learn how to bring the Schilling High-Light laser marking workstation into operation safely after installation or transport.
2
3 ----
4
5 (% class="box warningmessage" %)
6 (((
7 **Only qualified personnel may commission the system. Observe all safety notes before switching on.
8 Important: Remove the protective cap from the laser objective before starting the laser.**
9 )))
10
11 = Preconditions =
12
13 Confirm the following before applying power:
14
15 * All packaging material has been removed.
16 * All transport locks have been removed.
17 * The High-Light is standing upright in its intended operation position.
18 * Supply voltage and frequency have been checked against the machine requirements.
19 * The mains cable and plug are undamaged.
20 * The main switch is in the OFF position before connecting the power cable.
21 * The laser protection window is undamaged.
22 * Optical components are free from dust and contamination.
23 * The protective cover has been removed from the focusing objective.
24 * All required laser-safety measures have been implemented and verified.
25
26 The operating environments must also meet the High-Light requirements:
27
28 * Ambient temperature: +15 °C to +35 °C.
29 * Relative humidity: maximum 90%, non condensing.
30 * If the system has experienced significant temperature changes during transport, allow it to return to room temperature before commissioning.
31 * Avoid shocks, vibration and other mechanical stress.
32 * Keep the ventilation openings and filter areas of both 19" units unobstructed to prevent heat build-up.