Commissioning and First Start-Up

Version 1.6 von jadomatis am 2026/08/31 07:14

Description: Learn how to bring the Schilling High-Light laser marking workstation into operation safely after installation or transport.


Only qualified personnel may commission the system. Observe all safety notes before switching on.
Important: Remove the protective cap from the laser objective before starting the laser.

Preconditions

Confirm the following before applying power:

  • All packaging material has been removed.
  • All transport locks have been removed.
  • The High-Light is standing upright in its intended operation position.
  • Supply voltage and frequency have been checked against the machine requirements.
  • The mains cable and plug are undamaged.
  • The main switch is in the OFF position before connecting the power cable.
  • The laser protection window is undamaged.
  • Optical components are free from dust and contamination.
  • The protective cover has been removed from the focusing objectiv