4 4  
5 5  (% class="box warningmessage" %)
6 6  (((
7 -**Only qualified personnel may commission the system. Observe all safety notes before switching on.**
7 +**Only qualified personnel may commission the system. Observe all safety notes before switching on.
8 +Important: Remove the protective cap from the laser objective before starting the laser.**
8 8  )))
9 9  
10 -
11 += Preconditions =
12 +
13 +Confirm the following before applying power:
14 +
15 +* All packaging material has been removed.
16 +* All transport locks have been removed.
17 +* The High-Light is standing upright in its intended operation position.
18 +* Supply voltage and frequency have been checked against the machine requirements.
19 +* The mains cable and plug are undamaged.
20 +* The main switch is in the OFF position before connecting the power cable.
21 +* The laser protection window is undamaged.
22 +* Optical components are free from dust and contamination.
23 +* The protective cover has been removed from the focusing objective.
24 +* All required laser-safety measures have been implemented and verified.
25 +
26 +The operating environments must also meet the High-Light requirements:
27 +
28 +* Ambient temperature: +15 °C to +35 °C.
29 +* Relative humidity: maximum 90%, non condensing.
30 +* If the system has experienced significant temperature changes during transport, allow it to return to room temperature before commissioning.
31 +* Avoid shocks, vibration and other mechanical stress.