Zuletzt geändert von jadomatis am 2026/09/07 09:52

Zeige letzte Bearbeiter
1 **Description**: Learn how to receive, inspect, unpack, move, and install the Auto-Light before commissioning. Apply the same checks after any relocation.
2
3 {{toc/}}
4
5 (% class="box errormessage" %)
6 (((
7 **Class 4 integration laser: **Transportation and installation may be performed only by qualified personnel. Do not apply power until the Auto-Light and the host machine have been mechanically and electrically installed and all required laser-safety measures are ready for validation.
8 )))
9
10 ----
11
12 = Delivery Inspection =
13
14 Inspect the shipment immediately after unloading and before installation:
15
16 * Check the Auto-Light and all supplied components for visible transport damage.
17 * Check accessible screws and threaded connections for signs of movement or loosening.
18 * Compare the shipment with the order and delivery documents; the actual configuration and options may differ from the manual's standard-configuration list.
19 * If anything is damaged or missing, record it in writing, note it on the freight documents, take photographs, and send the report to Schilling Marking Systems.
20
21 (% class="box warningmessage" %)
22 (((
23 **Protect the optics: **Keep the lens-unit or objective protection cover installed until the marking head is in its final installed position. Clean, undamaged optics are required for correct marking performance
24 )))
25
26
27
28 = External Transportation =
29
30 * Keep the carton upright and firmly secured to the pallet.
31 * Secure the palletised shipment against sliding and tipping throughout transport.
32 * Use a forklift suitable for the weight and delivered configuration when unloading the palletised carton.
33 * Protect the shipment from strong vibration, shock, contamination, and weather exposure.
34
35
36
37 = Unpacking =
38
39 Two qualified people are required to remove the transport packaging.
40
41 1. Place the carton and pallet upright on level ground using a suitable forklift.
42 1. Stabilise the load, then release the black tensioning straps.
43 1. Remove the carton and packing sections carefully so that no section tips or falls.
44 1. Remove the remaining packaging and transport restraints only when the equipment is supported and ready for installation.
45 1. Retain reusable packaging and every delivered transport restraint for future shipment or long-distance relocation.
46
47 (% class="box warningmessage" %)
48 (((
49 **Handling rule: **Keep the Auto-Light upright. Avoid mechanical loads, vibration, and impact; the system contains high-quality electrical and optical components.
50 )))
51
52
53
54 = In-Plant Transportation =
55
56 1. Stop the process and set the rear main switch to 0 (OFF).
57 1. Disconnect the electrical supply cable.
58 1. Disconnect and remove the extraction system where fitted, following the extraction supplier's instructions.
59 1. Keep the equipment upright and slightly lift the supported assembly with handling equipment suitable for its weight and configuration.
60 1. Move it without strong vibration or shock and place it on a level, clean installation surface.
61 1. After relocation, realign the system, repeat the initial electrical commissioning procedure, and perform a controlled functional test.
62
63
64
65 = Installation-Site Requirements =
66
67 (% class="table-condensed table-striped" style="width:1272px" %)
68 |(% style="width:299px" %)**Requirement**|(% style="width:971px" %)**Installation criterion**
69 |(% style="width:299px" %)Environment|(% style="width:971px" %)+15 °C to +35 °C; relative humidity no higher than 90%, non-condensing.
70 |(% style="width:299px" %)Acclimatisation|(% style="width:971px" %)After a major temperature change, allow the equipment to return to room temperature before commissioning.
71 |(% style="width:299px" %)Support|(% style="width:971px" %)Upright, level, clean, stable, and suitable for the delivered configuration.
72 |(% style="width:299px" %)Cooling|(% style="width:971px" %)Provide adequate air to both 19-inch rack units; keep ventilation openings and filter mats unobstructed.
73 |(% style="width:299px" %)Extraction|(% style="width:971px" %)Provide extraction suitable for the gases, vapours, aerosols, and dust generated by the material and process.
74 |(% style="width:299px" %)Safety|(% style="width:971px" %)Complete the host enclosure, access control, emergency-stop functions, shutter interlocks, emission warning, and other required safeguards.
75
76
77
78 = Placement and Service Clearance =
79
80 Use the delivered drawings for the final mounting design. The following illustration is a planning summary and does not replace the configuration-specific drawings.
81
82 [[image:1788766589748-480.png]]
83
84
85 = Mechanical and Electrical Installation =
86
87 1. Remove all remaining packaging and transport restraints, then place and secure the equipment upright according to the approved machine design and delivered drawings.
88 1. Verify that the connection voltage and frequency match the system data.
89 1. Inspect the mains cable and plug for damage and correct specification. Keep the rear main switch at 0 (OFF) before connecting the mains cable to the Auto-Light or supply socket.
90 1. Complete the approved X1 safety and production-interface wiring. Connect X2 only for the axes included in the validated configuration.
91 1. Route and secure the approved USB, Ethernet, HDMI, axis, safety, power, extraction, and fibre connections so they are protected from damage and do not obstruct cooling or service access.
92 1. Inspect any installed laser-protection glass for damage and confirm that the complete host-machine safeguarding is ready for formal validation.
93
94
95
96 = Installation Completion Check =
97
98 Before the system is commissioned, confirm all of the following:
99
100 * The mechanical installation is complete, aligned, secure, and free from transport restraints.
101 * The electrical installation is complete and the input voltage is correct.
102 * The optics are free from dust and contamination; remove the focusing-objective protection cover only when final placement and inspection are complete.
103 * The environmental conditions, cooling airflow, and extraction comply with the approved design.
104 * The responsible personnel understand the applicable laser-safety requirements.
105 * Every required laser-safety measure has been implemented and is ready for verification by an authorised person.
106
107 (% class="box errormessage" %)
108 (((
109 **Commissioning hold point: **Do not switch on the Auto-Light until an authorised person has checked every laser-safety precaution and confirmed compliance. Then follow the separate Commissioning and First Start-Up article; after relocation, complete the same electrical commissioning and functional-test sequence again.
110 )))
111
112
113
114 = Long-Distance Transport =
115
116 Repack the Auto-Light as originally delivered, using the original carton, pallet, packing sections, straps, and transport restraints. The source manual specifically mentions a door restraint; install it when the delivered configuration includes an enclosure door. For other configurations, reinstall every original restraint supplied with that system.
117
118 (% class="box infomessage" %)
119 (((