Changes for page Commisioning and First Start
Last modified by jadomatis on 2026/09/07 09:02
Summary
-
Page properties (3 modified, 0 added, 0 removed)
Details
- Page properties
-
- Title
-
... ... @@ -1,0 +1,1 @@ 1 +Commisioning and First Start - Parent
-
... ... @@ -1,0 +1,1 @@ 1 +Schilling Marking Systems Auto-Light.Getting Started.WebHome - Content
-
... ... @@ -1,0 +1,95 @@ 1 +**Description**: Learn how to Commission the Auto-Light safely after transport, installation, integration, or relocation. Complete every integration-safety check before power is applied, then perform the first electrical start-up and controlled functional test. 2 + 3 +(% class="box warningmessage" %) 4 +((( 5 +**Class 4 integration laser: **Only trained and authorized personnel may commission the Auto-Light. Do not switch on the system until the protective enclosure, access safeguards, emergency-stop circuits, shutter circuits, emission warning, extraction, and all site-specific laser-safety measures have been completed, tested, documented, and accepted by an authorized person. 6 +))) 7 + 8 += Preconditions (Before Switching On) = 9 + 10 +Confirm all of the following before applying power: 11 + 12 +* Remove all packaging and transport restraints. Position the supplied equipment upright on a stable installation surface and complete the mechanical installation. 13 +* Verify that the mains voltage and frequency match the delivered system data. Keep the rear main switch in the OFF position while making or checking connections. 14 +* Inspect the mains cable and plug. Do not use the system if either is damaged, incorrectly specified, or insecurely connected. 15 +* Confirm that the X1 safety and production interface is wired to the approved external safety circuit, including both emergency-stop channels and both shutter channels. 16 +* Confirm that opening the protective enclosure or guard interrupts the shutter circuit. Test emergency-stop acknowledgement and all required safety-status signals before enabling laser operation. 17 +* If X2-controlled axes are installed, verify the approved axis wiring, direction, step, and zero-signal configuration before commanding movement. 18 +* Inspect any installed laser-protection window or enclosure glazing for damage. The protection must match the installed wavelength and power. 19 +* Ensure the focusing objective and other optical components are clean and free from dust. Leave the objective protection cap in place until immediately before start-up. 20 +* Provide unobstructed airflow at the 19-inch rack ventilation openings and filter mats. Do not operate the system if heat can accumulate. 21 +* Confirm an ambient temperature of +15 °C to +35 °C and relative humidity no higher than 90%, non-condensing. Allow the system to return to room temperature after major temperature changes. 22 +* Start and verify the approved extraction system for the material and process before any test marking. 23 + 24 +(% class="box warningmessage" %) 25 +((( 26 +The Auto-Light may be switched on only after an authorized person has checked the complete integrated installation and confirmed that the laser-safety measures comply with the applicable requirements. 27 +))) 28 + 29 + 30 + 31 += Electrical Start-Up = 32 + 33 +**Before starting: **Remove the protection cap from the laser objective. Never energize the laser with the objective cap fitted. 34 + 35 +1. Confirm that the integrated protective enclosure is closed, all safety circuits are ready, and extraction is running. 36 +1. Set the main switch on the rear of the Auto-Light rack to I (ON). 37 +1. Turn the laser key switch on the front of the rack to I. 38 +1. Observe the system status. If the system does not reach the expected ready state, switch it off and correct the cause before continuing. 39 + 40 +[[image:1788521448348-845.png]] 41 + 42 + 43 + 44 + 45 +[[image:1788521448357-184.png]] 46 + 47 + 48 += Software and Device Connection = 49 + 50 +1. ((( 51 +Start the approved workstation and open AnyMarker Designer. 52 +))) 53 +1. Verify communication with the Auto-Light controller and confirm that the expected device configuration and approved parameters are available. 54 +1. If communication is not established, stop the procedure, switch the Auto-Light off, and check the approved USB or Ethernet connection before restarting. 55 + 56 +For software-specific steps, use the **[[AnyMarker Designer XWiki>>url:https://docs2.anymarker.de]]**. This article does not replace the current software instructions. 57 + 58 + 59 += Initial Checks With the Pilot Laser = 60 + 61 +* Load or create an approved test layout in AnyMarker Designer. 62 +* Use the Pilot function to display the marking field without production-laser emission. 63 +* Verify the orientation and position of the projected field on the test workpiece while the protective enclosure remains closed. 64 +* Stop if the pilot outline, axis movement, or workpiece position does not match the validated setup. 65 + 66 + 67 + 68 += Focus and Workpiece Positioning = 69 + 70 +1. Secure the test workpiece or fixture in the approved marking position. 71 +1. Adjust the electrically controlled Z-axis until the specified focus distance is reached. The correct focus distance is required for a permanent, legible mark. 72 +1. Use the pilot outline and the approved focus method to confirm the marking location and focus before permitting production-laser emission. 73 + 74 + 75 + 76 += First Functional Test = 77 + 78 +1. Select a verified parameter set for the test material and confirm that extraction is operating. 79 +1. With the protective enclosure closed and all safeguards active, perform a short test mark on an approved sample. 80 +1. Monitor the ready, busy, end, shutter, and emergency-stop status signals used by the integrated machine. 81 +1. Inspect the result for position, focus, legibility, contrast, and unwanted thermal effects. Correct the setup only after laser emission has stopped. 82 +1. Record the accepted hardware configuration, software/device connection, safety-test result, and approved marking parameters before handing the system over for operation. 83 + 84 +(% class="box warningmessage" %) 85 +((( 86 +**Stop immediately: **If a safeguard, shutter circuit, emergency-stop function, status signal, axis, extraction system, or optical component behaves unexpectedly, stop commissioning and isolate the equipment. Do not bypass the fault to complete the test. 87 +))) 88 + 89 + 90 + 91 += Controlled Shutdown After the Test = 92 + 93 +1. End the marking command and confirm that laser emission has stopped. 94 +1. Set the rear main switch to 0 (OFF). 95 +1. Front key switch can remain at I or be returned to 0. Follow the site's approved key-control and access procedure.