1 1  **Description**: Learn how to identify the Auto-Light X0 mains connection, X1 safety and production interface, and X2 axis interface. The pin assignments and diagrams are reproduced from the supplied operating manual in English.
2 2  
3 +{{toc/}}
4 +
3 3  (% class="box errormessage" %)
4 4  (((
5 5  **Qualified integration work only: **The manual diagrams are connection examples, not a complete safety design or permission to wire an energised system. An appropriately qualified integrator must design, calculate, isolate, wire, validate, and document the complete safety-related control system for the delivered machine.
... ... @@ -7,7 +7,6 @@
7 7  
8 8  ----
9 9  
10 -
11 11  = Connection Locations =
12 12  
13 13  X0 mains power, X1 safety and production I/O, and X2 axis control are located at the rear of the laser rack. USB, Ethernet, and HDMI connections support the delivered workstation, network, and display arrangement.
... ... @@ -134,4 +134,36 @@
134 134  |(% style="width:108px" %)24|(% style="width:174px" %)-|(% style="width:207px" %)Not connected
135 135  |(% style="width:108px" %)25|(% style="width:174px" %)-|(% style="width:207px" %)Not connected
136 136  
138 +
139 +
140 += X2 Functional Grouping =
141 +
142 +(% class="table-condensed table-striped" style="width:1125px" %)
143 +|**Axis / function**|(% style="width:391px" %)**Pin(s)**|(% style="width:481px" %)**Direction stated in manual**
144 +|X axis|(% style="width:391px" %)1 Direction; 2 Step; 9 Zero|(% style="width:481px" %)Outputs on all three pins, as stated
145 +|Y axis|(% style="width:391px" %)3 Direction; 4 Step; 11 Zero|(% style="width:481px" %)Direction/Step outputs; Zero input
146 +|Z axis|(% style="width:391px" %)5 Direction; 6 Step; 13 Zero|(% style="width:481px" %)Direction/Step outputs; Zero input
147 +|R axis|(% style="width:391px" %)7 Direction; 8 Step; 15 Zero|(% style="width:481px" %)Direction/Step outputs; Zero input
148 +|Reference|(% style="width:391px" %)17 GND; 19 +5 V|(% style="width:481px" %)Outputs, as stated
149 +|Not connected|(% style="width:391px" %)10, 12, 14, 16, 18, 20-25|(% style="width:481px" %)NC
150 +
151 +
152 +
153 += Integration and Commissioning Checks =
154 +
155 +* (((
156 +Confirm X1 is a 25-pin Sub-D socket and X2 is a 25-pin Sub-D plug before preparing mating connectors.
157 +)))
158 +* Keep safety functions, production commands, status monitoring, axis signals, and workstation connections identified separately in the electrical documentation.
159 +* Verify conductor identification, shielding, routing, protective bonding, connector retention, strain relief, and separation from interference sources for the delivered installation.
160 +* Validate both emergency-stop channels, both shutter channels, acknowledgement behavior, guard opening, status outputs, and prevention of unexpected restart before laser operation is released.
161 +* Confirm the External START/STOP logic and LASER READY/BUSY/END sequence against the host control specification without bypassing any safety permission.
162 +* For every installed axis, verify direction, step scaling, travel limits, zero/reference behavior, and safe motion before placing a workpiece in the marking area.
163 +* Document measured results and obtain the required approval for the complete integrated machine, not only the Auto-Light rack.
164 +
165 +(% class="box infomessage" %)
166 +(((
167 + **Troubleshooting boundary: **Operators may record external status and host messages. Pin-level measurement, connector removal, rewiring, safety-module work, and axis electrical testing require isolation and personnel authorized for the delivered integration. Use the Auto-Light Troubleshooting article for symptom-based diagnosis.
168 +)))