3.2 | 1 | This procedure describes how to bring the Multi-Light or Multi-Light PLUS workstations into operation safely after transport or installation. **Only qualified personnel **may commission the system. Observer all safety notes before switching on. |
| |
2.1 | 2 | |
| |
1.1 | 3 | = Preconditions (Before Switching On) = |
| 4 | |||
| 5 | Confirm the following before applying power: | ||
| 6 | |||
| |
2.1 | 7 | * **Electrical installation is correct**; mains **voltage and frequency **match the rating place. Main switch is OFF. |
| 8 | * **Protective housing** and **door interlocks** are intact; **laser viewing window** shows now damage. | ||
| 9 | * **Optics are clean**; remove any **transport/lens cover** only now. Avoid touching optics with bare hands. | ||
| 10 | * **Ambient conditions**: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. | ||
| 11 | * **Airflow **at 19" drawers is unobstructed; **filter mats** are clean to prevent heat build-up. | ||
| 12 | * **Fume extraction **is installed and operational (mandatory for personnel safety and to protect optics). | ||
| 13 | * Operator is familiar with **laser safety** requirements; responsibilities are defined. | ||
| |
3.3 | 14 | **Note**: The Multi-Light and Multi-Light PLUS both contain a **Class 4 **laser** **source operated as **Class 1** in the closed cabin. Never bypass safety devices. |
| |
1.7 | 15 | |
| 16 | |||
| 17 | |||
| |
1.8 | 18 | = Electrical Start-Up = |
| 19 | |||
| |
2.1 | 20 | 1. Connect the system to the specified **mains supply**. Ensure extraction is running. |
| 21 | 1. Set the **mains switch to ON**. Internal electronics initialize; status indicators light as described on the operator panel. | ||
| 22 | 1. Power on the **control PC** (or workstation) and peripherals needed for operation. | ||
| |
1.10 | 23 | |
| 24 | |||
| 25 | |||
| |
1.11 | 26 | = Software and Device Connection = |
| 27 | |||
| |
2.1 | 28 | 1. Launch the **AnyMarker Designer **software. |
| 29 | 1. Verify communication with the **laser controller** in the software (device connected, parameters readable). | ||
| 30 | If connection fails, switch **OFF**, check cabling and restart. | ||
| |
1.12 | 31 | |
| |
3.1 | 32 | {{warning}} |
| 33 | **Important: Only start the laser software when the laser is switched on. If the laser is switched on while the software is running, the system will not work.** | ||
| 34 | {{/warning}} | ||
| |
1.12 | 35 | |
| 36 | |||
| |
1.13 | 37 | = Initial Checks With Pilot Laser = |
| 38 | |||
| |
2.1 | 39 | * Load or create a **test layout** in AnyMarker Designer. |
| |
3.1 | 40 | * Enable the** pilot laser **to project contours on the workpiece; verify **orientation and placement** without laser emission. Keep the door closed. |
| |
1.14 | 41 | |
| 42 | |||
| 43 | |||
| |
1.15 | 44 | = Z-Axis Focusing = |
| 45 | |||
| |
2.1 | 46 | 1. Place the workpiece/fixture in the work chamber and close the **manual lift door**. |
| 47 | 1. Use the **automatic Z-axis** to set focus to the surface (per lens focal distance). Follow the on-screen/readout guidance for focal height. | ||
| |
1.16 | 48 | 1. Confirm best focus by pilot outline sharpness or focus gauge method recommended in the manual. |
| 49 | |||
| 50 | |||
| 51 | |||
| |
1.17 | 52 | = Parameter Verification = |
| 53 | |||
| |
2.1 | 54 | * Select a verified **marking parameter set** (power, speed, frequency, fill). Start with conservative energy to avoid burning or glare. |
| 55 | * Ensure extraction is active to remove **gases**, **vapors**, **aerosols**, **and dust** during test marking. | ||
| |
1.18 | 56 | |
| 57 | |||
| 58 | |||
| |
1.19 | 59 | = First Test Mark = |
| |
1.20 | 60 | |
| |
2.1 | 61 | 1. With the cabin closed and interlocks engaged, execute a **short test mark** on a sample of the target material. |
| 62 | 1. Observe quality and adjust **parameters **(e.g., reduce power/increase speed) as needed. Multiple **repetitions **may be used for depth, but monitor temperature to reduce fire risk. | ||
| 63 | 1. If unexpected behavior occurs, press **STOP**/**EMERGENCY-STOP**, investigate messages in **Notifications**, and correct the cause before resuming. | ||
| |
1.21 | 64 | |
| 65 | |||
| 66 | |||
| |
1.22 | 67 | = Post-Test Verification = |
| 68 | |||
| 69 | * Inspect the mark; check legibility/contrast. Clean light residue if necessary. | ||
| |
2.1 | 70 | * Re-check **filters**/**airflow **after prolonged tests. Excess dust must not accumulate. |
| 71 | * Document the **approved parameter set** for production. | ||
| |
1.23 | 72 | |
| 73 | |||
| 74 | |||
| 75 | = Normal Operation Handover = | ||
| 76 | |||
| |
2.1 | 77 | * Train operators on **door interlock**, **pilot laser**, **start**/**stop**, and **notifications **usage. |
| |
3.1 | 78 | * Emphasize daily** pre-shift checks **(visible damage, labels present, safety devices functional). |
| |
1.24 | 79 | |
| 80 | |||
| 81 | |||
| |
1.25 | 82 | = Shutdown (End of Day) = |
| 83 | |||
| 84 | 1. Stop software and close the project. | ||
| |
2.1 | 85 | 1. Turn the system **OFF **via main switch; power down extraction as specified. |
| 86 | 1. Clean the work area; never leave the machine **unattended **while powered. | ||