1.1 | 1 | = Preconditions (Before Switching On) = |
| 2 | |||
| 3 | Confirm the following before applying power: | ||
| 4 | |||
| |
1.3 | 5 | * Electrical installation is correct; mains voltage and frequency match the rating place. Main switch is OFF. |
| |
1.4 | 6 | * Protective housing and door interlocks are intact; laser viewing window shows now damage. |
| 7 | * Optics are clean; remove any transport/lens cover only now. Avoid touching optics with bare hands. | ||
| |
1.5 | 8 | * Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport. |
| |
1.6 | 9 | * Airflow at 19" drawers is unobstructed; filter mats are clean to prevent heat build-up. |
| 10 | * Operator is familiar with laser safety requirements; responsibilities are defined. | ||
| |
1.7 | 11 | Note: The Multi-Light contains a Class 4 source operated as Class 1 in the closed cabin. Never bypass safety devices. |
| 12 | |||
| 13 | |||
| 14 | |||
| |
1.8 | 15 | = Electrical Start-Up = |
| 16 | |||
| 17 | 1. Connect the system to the specified mains supply. Ensure extraction is running. | ||
| |
1.10 | 18 | 1. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel. |
| 19 | 1. Power on the control PC (or workstation) and peripherals needed for operation. | ||
| 20 | |||
| 21 | |||
| 22 | |||
| |
1.11 | 23 | = Software and Device Connection = |
| 24 | |||
| |
1.12 | 25 | 1. Launch the AnyMarker Designer software. |
| 26 | 1. Verify communication with the laser controller in the software (device connected, parameters readable). | ||
| 27 | If connection fails, switch OFF, check cabling and restart. | ||