Commissioning and First Start-Up

Version 1.10 by jadomatis on 2025/09/29 12:09

Preconditions (Before Switching On)

Confirm the following before applying power:

  • Electrical installation is correct; mains voltage and frequency match the rating place. Main switch is OFF.
  • Protective housing and door interlocks are intact; laser viewing window shows now damage.
  • Optics are clean; remove any transport/lens cover only now. Avoid touching optics with bare hands.
  • Ambient conditions: +15C to +35C. RH <90% non condensing; system acclimatized if temperature changed during transport.
  • Airflow at 19" drawers is unobstructed; filter mats are clean to prevent heat build-up.
  • Operator is familiar with laser safety requirements; responsibilities are defined.
    Note: The Multi-Light contains a Class 4 source operated as Class 1 in the closed cabin. Never bypass safety devices.

Electrical Start-Up

  1. Connect the system to the specified mains supply. Ensure extraction is running.
  2. Set the mains switch to ON. Internal electronics initialize; status indicators light as described on the operator panel.
  3. Power on the control PC (or workstation) and peripherals needed for operation.